Full closure: the A684 at Bellow Hill, east of Sedbergh, is scheduled to close continuously from Monday 14 September to Friday 16 October 2026 while a damaged culvert is reconstructed.
The closure applies to everyone, including pedestrians and cyclists. Excavation crosses the full carriageway, so do not expect to walk a bicycle through the works.
Visitors approaching Sedbergh from Garsdale, Hawes and the east need to allow for a substantial signed diversion. The timing overlaps the Sedbergh Walking & Wellbeing Festival and the launch of the Westmorland and Furness Way, but it does not mean Sedbergh town itself is closed.
A684 closure at a glance
- Closure point: Bellow Hill Culvert, between Long Holme and the entrance to West Bridge End
- What3words: ///driftwood.oven.smudges
- Dates: 14 September-16 October 2026
- Maximum programme: up to five weeks
- Closure hours: continuous, including outside the normal 8am-5pm working day
- Who is affected: motorists, buses, cyclists and pedestrians
- Additional closure: Danny Wheel Road at its eastern Bellow Hill junction
Where is Bellow Hill?
The work is on the A684 east of Sedbergh towards Garsdale Head. It is not in Sedbergh town centre and it is not the A683 approach from Kendal and the M6.
This distinction matters when planning a festival visit. A journey arriving from Kendal or Junction 37 via the A684/A683 west of Sedbergh may not cross the excavation, while a route from Hawes, Garsdale and parts of the Yorkshire Dales is directly affected.
Official signed diversion
Westmorland and Furness Council gives the signed diversion as:
- B6259 via Kirkby Stephen
- A685 via Tebay
- A683 into Sedbergh
- A684 back towards Garsdale on the appropriate side of the closure
Use the signed route in the direction shown on site. It is a long diversion because the Howgills and Dales offer few roads suitable for through traffic. Allow much more time than the closed A684 journey and do not use narrow lanes as a satnav shortcut.
High-vehicle restriction
The published diversion is not suitable for vehicles over 14ft 6in because of a low bridge on the A685. Drivers of high vans, coaches and commercial vehicles must obtain a suitable route before setting out rather than reaching the bridge and improvising.
Why walkers and cyclists cannot pass
The council needs to excavate across the full width of the highway to rebuild Bellow Hill Culvert. There is no residual strip of carriageway for a bicycle or pedestrian to use safely. The legal closure therefore applies to all highway users, even outside working hours.
Do not move barriers, enter the excavation or assume that quiet evenings create a safe passage. Anyone following a long-distance route that uses this road section must obtain an officially viable alternative from the route organiser.
Sedbergh Walking & Wellbeing Festival advice
The festival opens on Sunday 13 September and its main programme runs from 14 to 20 September, exactly when the closure begins. Individual walks and activities use different meeting points, so the effect depends on where that session starts.
- Check the meeting point on your booking, not simply “Sedbergh”.
- If approaching from the east, recalculate the journey using the signed diversion.
- Arrive before the stated registration or briefing time; leaders cannot delay a group for diverted traffic.
- Do not assume a walking event has permission to cross a closed public highway.
- Ask the organiser before changing a route or parking in a village not listed for the session.
Westmorland and Furness Way launch on 15 September
The official launch of the new long-distance Westmorland and Furness Way is connected to the festival on Tuesday 15 September. The road closure does not cancel the launch, but it changes travel for participants approaching Sedbergh from Garsdale or Hawes.
The trail and the highway scheme are separate. Use the event organiser's final instructions for the launch route and use the council notice only for road access. Never infer a walking diversion from the motor-traffic diversion.
Driving to Sedbergh from common directions
| Approach | Likely issue | Planning advice |
|---|---|---|
| Kendal / M6 Junction 37 | Usually approaches from west via A684/A683 without crossing Bellow Hill | Still check live traffic and allow event-day time |
| Tebay / Kirkby Stephen | Forms part of the signed diversion corridor | Expect extra diverted traffic |
| Garsdale / Hawes | Directly separated from Sedbergh by the works | Follow the full signed diversion; do not use minor lanes |
| High vehicle over 14ft 6in | Published diversion has a low A685 bridge | Obtain an alternative suitable route before travel |
What about Danny Wheel Road?
Danny Wheel Road is closed at its junction with Bellow Hill at the eastern end of the works for the duration. It should not be treated as a local escape around the excavation.
Separate later A684 work
The council's wider A684 programme also refers to later work at the Potgill Holme cattle grid during October and November, but confirmed dates were not part of the Bellow Hill update checked for this guide. Do not merge the two schemes or extend this closure beyond the published 16 October date without a new official notice.
Official source
Check Westmorland and Furness Council's live A684 repair update.
Information checked 8 September 2026. Construction dates, temporary traffic management and event arrangements can change; follow signs and your organiser's final joining instructions.